Is it possible to change Time Spent for task/subtask manually?
So for example when the time spent says 0:45:00 you edit it and change it into something else like for example 0:30:00.

Thanks.

Regards,

Gosa

Question information

Language:
English Edit question
Status:
Answered
For:
Task Coach Edit question
Assignee:
No assignee Edit question
Last query:
Last reply:
Revision history for this message
Frank Niessink (frank-niessink) said :
#1

Hi Gosa, the only way to change the time spent is to edit the effort record and change the start or end time of the effort tecord. To edit the effort records for the task open the task by double clicking it and go to the effort tab (you may have to click the little black triangle to see more tabs).